21 days advance notice is required.

Use the chart below to estimate the days needed.

 

 

Estimating How Many Days The Install Will Take

100 units

1 installer

1 day

200 units

1 installer

2 days

300 units

1 or 2 installers

3 or 2 days

400 units

2 installers

2 days

500 units

2 installers

2.5 days

600 units

2 or 3 installers

3 or 2 days

700 units

2 or 3 installers

3.5 or 2.5 days

800 units

3 installers

3 days

900 units

3 installers

3.5 days

1000 units

3 or 4 installers

4 or 3 days

1100 units

3 or 4 installers

4 or 3 days

1200 units

3 or 4 installers

4.5 or 3.5 days

1600 units

4 installers

5 days

2000 units

4 installers

6.5 days

BKR Installations reserves the right to determine the number of installers and actual install days needed.